A Better Way to Schedule Installation

Instead of telling customers:

“You can use it immediately.”

A professional installation schedule is:

Stage 1 — Installation Complete

Turf is positioned, seams aligned and perimeter secured.

Stage 2 — Initial Inspection

Check:

  • wrinkles,
  • seam alignment,
  • edges,
  • drainage,
  • visible defects.

Stage 3 — Adhesive Curing

Allow the adhesive to reach the manufacturer’s specified condition.

Stage 4 — Final Inspection

Check seam strength, perimeter fixing and overall surface condition.

Stage 5 — Open for Normal Use

Only after the installer confirms that the system is ready.

This approach is more reliable than using a universal 12-hour or 24-hour rule.


Installation Conditions Matter

FactorPotential Effect
TemperatureCan change adhesive reaction and curing rate
HumidityMay affect certain adhesive systems
Substrate moistureImportant for adhesive bonding
RainCan interfere with some fresh adhesive systems
WindCan affect positioning before bonding
Base conditionDetermines long-term stability
Adhesive typeOne of the biggest variables in curing time

For this reason, a project should specify the acceptable installation conditions before work begins.

agsturf Avatar

Leave a Reply

Your email address will not be published. Required fields are marked *

agsturf

AGS Turf supplys highest quality artificial grass with factory direct price.
Our installation team Artificial Grass Solution became a licensed contractor in 2016 and ranked five-star on Yelp!